From January 5 through 8, Bartlett Services installed scaffolding in the
MiniBooNE tank. These pictures show progress during the first day and
a half (when I had to leave). By the end of Day 2, the framing was complete
to the top of the tank. On Day 3, the remaining decking and the planking
on the outriggers were installed. Day 4 was mostly used for cleanup.
Bartlett did a fabulous job for us!
| (l) Scaffolding parts filling Roundhouse before installation. (r) The Marines lowering a load of decking. |
![]() |
![]() |
||
| (l) Day 1: getting started with framing: 11:00 am. (r) Progress accelerates when first square established. |
![]() |
![]() |
||
| (l) Most of the lowest level in: . (r) Start of stairway and second level: ~7:30 pm. |
![]() |
![]() |
||
| (l) Day 2: stair treads and more of level 2 in. (r) Level 2 decking and stair to level 3 complete: 2:30 pm. |
![]() |
![]() |
||
| Detail of scaffolding. The feet had glued-on rubber pads to protect the tank. Only the feet touch the tank. | ![]() |