Barrel RPC Acceptance Criteria
| Parameter | Value | Comments |
|
Gas leak rate | <.05 cc/min | This is about the limit
of our measurement. We may tighten this if an improved method can be devised.
|
|
Chamber expansion | r>0.6 mm-Aq/cc |
Use's Gotow-san's definitionm for r |
|
Gas blocks | Al | We plan to do this anyway. |
|
Efficiency | > 85% |
1) Single-layer efficiency. 2) Vth=30 mV |
|
Efficiency | > 95% |
1) Super-layer efficiency. 2) Vth=30 mV |
|
HV plateau | > 500 V |
1) It should be possible to obtain >85% efficiency over a range of voltages
that is at least this wide. 2) Vth=30 mV |
|
X vs Y | see note |
1) No region away from the center of the chamber having area 30x30 cm**2
or greater should have an efficiency smaller than 75%. Test done for each
RPC within the superlayer.
2) This can be done by visual inspection (i.e.,
test is not meant to be quantitative) of
Steve's x vs. y plots.
3) Vth=30mV |
|
Bad strips | none |
"Dead" means not connected or shorted. |
|
Current | <1.5 uA/m**2 |
1) This is current draw from +HV side. If -HV side is used the current in the
1 Gohm resistor should be subtracted. 2) HV = 9KV (total) 3) It is assumed that
a training period may be required to attain this value. 4) The current values
are averages of about 50 samples.
|
|
Max HV | +9.5KV |
A short test should be done to verify that there is no breakdown
at this voltage. |
|
Test duration | 10 days |
Chamber should operate in a stable fashion, satisfying the above
criteria for this length of time. |
|
Overall | - |
Chambers will be rated as good, fair, or poor, according to how close they
are to failing the various cuts listed above. Chambers rated as fair will
be installed as a last resort. Chambers rated as poor will not be installed.
|
|
|